CENTRAL TERMOELECTRICA TOCOPILLA SEAPORT |
||
|
Location |
Tocopilla, II Region - CHILE |
|
|
Characteristics |
Mechanized wharf for coal unloading and storage, founded on driven steel piles anchored to the rock, with an access bridge of 192 m long by 7 m wide and an unloading platform of 82 m long by 20 m wide, that supports two unloading cranes of 600 ton/hr. each. The port may berth ships up to 60,000 DWT. Construction of all the necessary infrastructure for the coal storage and handling such as level spaces, internal roads, laboratories, control rooms, store houses, environmental control system, diesel storage reservoir and others. |
|
|
Work's Main Figures |
Embankment |
92,300 m3 |
|
|
Rock Protection |
56,000 m3 |
|
|
Production and placement of Dolloses 1.83 tons |
1,882 un. |
|
|
Production and placement of Dolloses 5.50 tons |
5,879 un. |
|
|
Rock Excavation |
18,000 m3 |
|
|
Concrete Foundations |
15,000 m3 |
|
|
Supply and Driving of Steel Piles |
2,720 m |
|
|
Rock Drilling for Pile Anchorage |
800 m |
|
|
Fabrication and installation of Anchorage |
1,400 m |
|
|
Supply and erection of Steel Structures for Belt Conveyors & Transfer Towers |
1,980 ton |
|
|
Supply and structural erection of Diesel Storage Reservoir |
728 ton |
|
Type of Contract |
Procurement and Construction |
|
|
Execution period |
July 1985 - October 1987 |
|
|
Owner |
Codelco Chile, División Tocopilla |
|