ARAUCO II PROJECT - VIII REGION |
||
|
Location |
Carampangue, VIII Region - CHILE |
|
|
Characteristics |
Construction of all the Civil Works, Structural, Mechanical, Electrical erection and complete Piping, for a plant to produce 1,000 ton/day of whitewash cellulose. | |
|
Work's Main Figures |
Excavation |
56,528 m3 |
|
|
Compacted backfill |
54,255 m3 |
|
|
Structural Concrete |
80,000 m3 |
|
|
Anchor Bolts and Inserts |
315 ton |
|
|
Steel Structures Erection |
8,500 ton |
|
|
Carbon Steel Tank Erection |
2,000 ton |
|
|
Built Surface |
46,944 m2 |
| Slabs Structural Faceplate PV6 1mm |
12,300 m3 |
|
| Steel Pipe Erection |
557,500 m.in. |
|
| Complete Mechanical, Electrical and Piping Erection for all production areas. | ||
|
Execution period |
September 1989 - September 1991 |
|
|
Owner |
Celulosa Arauco y Constitución S.A. |
|